The Building Process

The following is a general timeline for the building process.  The intention of it is to assist buyers with the sequence of events when building a Goetzmann Home.  In no way does this represent concrete dates .  Typically, our homes take 5-7 months from contract date to close.

 

MONTH 1

1.       The signed contract is submitted to Phil Goetzmann

2.       Phil submits the information to our architect and they develop the site plan

3.       The site plan is given to Regional Building for approval

4.       If applicable, the site plan must be approved by the City of Colorado Springs or the Town of Monument, depending on the
            location of your new home.

5.       Once it has been approved, the appropriate permits are pulled

6.       Within a week of the approval from Regional Building the lot will be staked

7.       Color section should be made

MONTH 2

1.       1-2 weeks after the lot is prepared, the footings and
            foundation are poured

2.       Foundation walls will be sealed and the peripheral
           drain will be installed before the foundation is
           back-filled

3.      Framing will begin

MONTHS 3-4

1.       Framing will be completed

2.       Mechanicals begin (Plumbing, heating and electrical)

3.       Once framed, you will be given notice of the dates for your electrical and low-voltage walk-through.

a.      Call Lindsay at Home Lighting to have her attend the electrical walk-through

b.      Select your light fixtures

MONTHS 4-6

1.       The insulation is installed and the drywall begins

2.       Interior finishes begin (Painting, cabinets, hardwood, etc.)

3.       Exterior concrete poured