The Building Process
The following is a general timeline for the building process. The intention of it is to assist buyers with the sequence of events when building a Goetzmann Home. In no way does this represent concrete dates . Typically, our homes take 5-7 months from contract date to close.

MONTH 1
1. The signed contract is submitted to Phil Goetzmann
2. Phil submits the information to our architect and they develop the site plan
3. The site plan is given to Regional Building for approval
4.
If
applicable, the site plan must be approved by the City of Colorado Springs
or the Town of Monument, depending on the
location of your new home.
5. Once it has been approved, the appropriate permits are pulled
6.
Within a
week of the approval from Regional Building the lot will be staked
7. Color section should be made
MONTH 2
1.
1-2 weeks
after the lot is prepared, the footings and
foundation are poured
2.
Foundation walls will be sealed and the peripheral
drain will be installed
before the foundation is
back-filled
3. Framing will begin
MONTHS 3-4
1. Framing will be completed
2. Mechanicals begin (Plumbing, heating and electrical)
3. Once framed, you will be given notice of the dates for your electrical and low-voltage walk-through.
a. Call Lindsay at Home Lighting to have her attend the electrical walk-through
b. Select your light fixtures
MONTHS 4-6
1. The insulation is installed and the drywall begins
2.
Interior
finishes begin (Painting, cabinets, hardwood, etc.)
3. Exterior
concrete poured